THE railway between Llandudno Junction and Blaenau Ffestiniog on the Conwy Valley Line is expected to open in a matter of days. 

Emergency repairs are taking place; The line was closed on Tuesday afternoon (April 9) after river flooding washed away ballast (the stones that support the track) near Dolgarrog station.

Engineers from Network Rail will now work around the clock to ensure the railway can reopen safely on Saturday, April 13. 

They will install more than 200 tonnes of new ballast using road-rail vehicles, with the work expected to be completed in time for the start of train services on Saturday morning.

Rachel Heath, Network Rail Wales and Borders operations director, said: “We’re sorry to passengers affected by the closure of the Conwy Valley Line.

RELATED NEWS

“Our teams are on site and working to get the line opened as soon as possible. We advise passengers to check before they travel at www.nationalrail.co.uk."

While the railway is closed, there will be changes to journeys for Transport for Wales passengers, with rail replacement buses operating between Llandudno Junction and Blaenau Ffestiniog, stopping at all stations: Glan Conwy, Tal-y-cafn, Dolgarrog, North Llanrwst, Llanrwst, Bewys-y-coed, Pont-y-pant, Dolwyddelan, Roman Bridge and Blaenau Ffestiniog.

The only exception is the 5.30am service each day, which will stop only at Tal-y-cafn, North Llanrwst, Llanrwst and Betws-y-Coed.